Belt conveyors rarely fail because the steel was too light or the motor too small. They fail in the first weeks because the frame was out of line, an idler was installed backwards, the belt was tensioned by guesswork, or the conveyor was handed over after an hour of empty running. This guide is the installation and commissioning procedure our service engineers use in the field, condensed from the Tianyi belt conveyor installation manual. It covers preparation, the erection sequence, the tolerances that keep a belt centred, drive and pulley alignment, idler orientation, take-up tensioning, the two-hour no-load run, the staged load test, and the maintenance schedule that starts on day one. If you want the short version first, read our belt conveyor installation guide; this article is the factory-level detail behind it.

In this article

1. Why installation quality decides whether the conveyor works 2. Before erection: documents, unpacking and foundations 3. The erection sequence: from centreline to belt splice 4. Frame accuracy: the tolerances that prevent mistracking 5. Drive unit and pulley installation 6. Idler installation: orientation, height and transition zones 7. Take-up systems and belt tensioning 8. Accessories: cleaners, skirtboards, safety devices and guards 9. No-load and load commissioning: the staged test procedure 10. Operation, inspection and maintenance after handover Frequently asked questions

1. Why Installation Quality Decides Whether the Conveyor Works

A belt conveyor is a system, not a machine. The belt is both the carrying surface and the traction element, and it only runs centred and at full capacity if four things are true at once: the frame is straight, the pulleys are square to the centreline, the idlers are at the right height and angle, and the tension is correct. Get any one of them wrong and the belt will tell you — usually by moving sideways.

The problems that appear during the first weeks of operation are overwhelmingly installation problems, not design problems:

The first rule of commissioning: a belt that mistracks by more than 5% of its width is not yet a belt problem. It is an alignment, tension or loading problem, and it should be corrected before the conveyor is run loaded.
Belt conveyor head station during commissioning, with drive unit, guarded head pulley and engineers checking belt tracking
Figure 1. A belt conveyor head station during commissioning: drive unit and gearbox at the left, guarded head pulley, belt running on the carrying idlers, and the inspection team checking tracking and belt condition before the load run.

2. Before Erection: Documents, Unpacking and Foundations

Installation starts before the first bolt is tightened. The manual is explicit about the preparation stage because most rework later traces back to something that was skipped here.

Do not start erection until the foundation has been accepted and the centreline has been established. A conveyor built from a wrong centreline cannot be corrected by adjusting idlers afterwards — the error is in the structure.

3. The Erection Sequence: From Centreline to Belt Splice

The order matters. Each step assumes the previous one is complete and checked, and doing them out of order is how frames end up stressed and belts end up twisted.

  1. Mark the centreline and benchmark elevation. Set out the head, intermediate and tail frame positions from the same centreline, and establish a level datum that every frame section can be measured against.
  2. Install the frame: head frame → intermediate frames → tail frame. Align and temporarily bolt the sections. Do not final-tighten until the whole line has been checked for straightness and squareness.
  3. Install the return idlers and the bend and tail pulleys. These set the lower line of the belt and the return path.
  4. Lay the belt out on the return (flat) idlers. On an incline, secure the upper end of the belt before releasing it — an unsecured belt on a slope can run away and is a serious hazard.
  5. Install the carrying idler sets. Check tilt direction and height as you go; correcting them now is far easier than after the belt is tensioned.
  6. Install the take-up, the drive pulley and the drive unit. Align the drive pulley to the centreline before the drive is coupled to it.
  7. Route the belt over the head and tail pulleys. Check that it is not twisted and that it sits correctly in every trough.
  8. Splice the belt. Whether the splice is vulcanised or mechanical, check its squareness and centreline. A splice that is not square will steer the belt for the rest of its life.
  9. Tension the belt with the take-up. Tension both edges equally and check tracking at low speed before the full run.
  10. Install the cleaners, backstop, skirtboards, guide chutes, guards and covers. These are part of the machine, not an afterthought; a conveyor commissioned without them is not ready to run.
Final tightening comes last. Level and square the frame, check the diagonals, then tighten the structural bolts in a systematic pattern. Tightening as you go locks in errors that are expensive to remove later.

4. Frame Accuracy: The Tolerances That Prevent Mistracking

The belt follows the structure. If the frame weaves, the belt weaves. That is why the installation manual specifies frame straightness as a measured tolerance rather than a matter of judgement.

4.1 Centreline straightness

Conveyor length (m)Permissible centreline deviation (mm)
≤ 10010
> 100 to 30030
> 300 to 50050
> 500 to 1,00080
> 1,000 to 2,000150
> 2,000200

Two additional rules apply on top of the table. In any 25 m length, the centreline deviation must not exceed 5 mm. And on a reversible conveyor, where the belt can mistrack in either direction, the installation must be tighter: the straightness is held to two-thirds of the values above.

4.2 Intermediate frame accuracy

CheckTolerance (mm)
Cross-beam spacing2.0
Longitudinal beam spacing2.0
Difference between the diagonals of the longitudinal beam holes (x − y)2.0
Height difference between the two side longitudinal beams (e)2.0
Height difference across a longitudinal beam joint1.0

Measure with a tensioned piano wire or laser for the centreline, a spirit level or laser for elevation, and a tape for the diagonals. Record the readings section by section; a frame that is within tolerance at every joint but cumulative out of line over 200 m is still out of tolerance.

Reversible conveyors are the hardest case. A one-way conveyor can sometimes be trained to compensate for a small frame error. A reversible conveyor cannot, because the correction that helps in one direction hurts in the other. That is why the tolerance is reduced to two-thirds.

5. Drive Unit and Pulley Installation

The drive unit should be assembled at the factory wherever transport allows, and connected to the drive pulley on site as a complete unit. Large, heavy drives that cannot be shipped assembled are sent in components and assembled on site, following the individual manuals for the motor, reducer, brake, backstop, fluid coupling, couplings and motorised pulley.

5.1 Pulley installation

The lagging is directional and the bearings are not. Two of the most common commissioning errors on a drive pulley are fitting the herringbone lagging backwards and over-packing the bearing housings. Both are invisible at handover and expensive in service.

6. Idler Installation: Orientation, Height and Transition Zones

Idlers do three jobs: they support the belt and the load, they shape the belt into a trough, and — with the right tilt — they help keep it centred. Installing them is simple; installing them correctly is where most mistracking is prevented.

Idler typeWhere it is usedInstallation point to watch
Troughing idlers, 30° / 35° / 45°Carrying side, normal runningCorrect trough angle for the belt and material; all three rollers in contact
Forward-tilted troughing idlersCarrying side where tracking needs helpSide rollers tilted 1.5° in the direction of belt travel
Transition idlers, 10° / 20° / 30°Between the head or tail pulley and the first full troughing setProgressive opening of the belt; reduces edge tension and spillage
Impact idlers (rubber-ring)Under the loading chuteAbsorbs falling-material impact and protects the belt carcass
Self-aligning idlersCarrying and return side, long runsCorrect orientation; the steering action only works in one direction
Return idlers: flat, V, forward-tilted V, spiralReturn sideV and tilted types must face the direction of return belt travel
Inclined belt conveyor inside a steel gallery with yellow walkway railing and idlers visible along the carrying side
Figure 2. An inclined belt conveyor inside a steel gallery, with a stepped walkway alongside. On an incline, idler tilt, belt tension and take-up travel all have to be right together, or the belt will drift to the low side under load.

7. Take-Up Systems and Belt Tensioning

The take-up does two things: it provides the tension the drive needs to transmit power without slipping, and it absorbs the elongation the belt develops over its life. The right type depends on the length, power and duty of the conveyor.

Take-up typeTypical dutyTension rangeTravel
Screw take-upShort, low-power conveyors9–37 kN, depending on belt widthSet by screw; limited
Gravity take-upGeneral duty; compensates automatically for belt elongation8–63 kNVariable
Gravity trolley or towerLong, high-power inclined conveyors8–63 kN3 / 4 / 5 m (tower)
Fixed winch take-upLong distance, high capacity and high tension30–150 kN (six-part rope fall)Up to 17 m
Too little tension causes slip, heat and edge damage. Too much tension overloads bearings, stretches the belt and shortens splice life. Set it to the design figure, then verify it under full load — not on an empty belt.

8. Accessories: Cleaners, Skirtboards, Safety Devices and Guards

The accessories are what turn a running belt into a production machine. They are also the parts most often left until last — and the parts whose absence causes the most spillage, dust and injuries.

9. No-Load and Load Commissioning: The Staged Test Procedure

Commissioning is done in two stages, and the first stage is not optional. The conveyor runs empty for at least two hours, is adjusted, and only then is loaded — in steps.

9.1 Checks before the first start

9.2 No-load run: at least two hours

Run the conveyor empty and watch it. The manual lists what to look for, and each item is a question with a yes or no answer:

9.3 Load run: 20% → 50% → 80% → 100%

Load the conveyor in steps, with at least two hours of continuous running at each step. Start at about 20% of rated load, then 50%, 80% and 100%. Where the process requires it, add a 110–125% full-load start and run test. Loading gradually lets a fault appear at a controlled load, where it can be corrected, instead of at full production, where it becomes damage.

SymptomLikely causeAction
Belt slips at the drive pulley on startInsufficient tension; wet or dirty laggingIncrease take-up tension gradually; clean and dry the lagging
Material sits off-centre on the beltChute discharging to one sideAdjust the adjustable baffle in the chute
Belt mistracks by more than 5% of widthIdler or pulley misalignment; off-centre load; low tension; belt or splice not straightCentre the load; adjust carrying and return idlers and the head and tail pulleys; raise tension; check belt and splice straightness and re-splice if needed
An idler does not rotateSeized bearing or damaged rollerFree it or replace the idler
Abnormal drive noise or temperatureCoupling misalignment; low oil; incorrect fluid-coupling fillRe-align the coupling; check oil level; set the coupling fill
Carryback and spillage at the headCleaner poorly set or worn; skirt seal openAdjust or replace the cleaner blades; re-seal the skirtboard
Uneven current between motors on a multi-driveUnequal fluid-coupling fillBalance the fill until the currents match

While the conveyor is loaded, also measure belt speed, throughput, start and stop times, and motor current at rated load. On a multi-drive conveyor, the current is the simplest indicator of whether the motors are sharing the load; if they are not, balance them with the fluid-coupling fill.

Load in steps, not all at once. A conveyor that is loaded to 100% on its first run hides its faults until they are expensive. A staged load test finds them at 20%.

10. Operation, Inspection and Maintenance After Handover

The manual is clear that the service life of a belt conveyor depends as much on operation and maintenance as on the equipment itself. The handover is the start of that regime, not the end of the project.

10.1 Operating rules

10.2 Operator inspection

During operation, the operator should patrol the line and watch the items that fail first: motor temperature and noise; brake action and brake-drum contact; reducer oil level and noise; belt tracking and belt damage; bearing temperature and noise; the condition of each transfer point; chute blockage; the condition of pulleys, idlers, cleaners and the take-up; housekeeping at the head, tail and drive frames; and the state of the electrical controls. Record abnormalities, and stop immediately in an emergency.

10.3 Maintenance intervals

In addition to daily inspection, a minor service is normally carried out monthly and a major overhaul every six to twelve months, shortened or extended to suit the site and the duty.

ServiceTypical scope
Minor service (monthly)Belt wear check and repair; reducer oil top-up or change; brake shoe and drum wear; pulley lagging wear and repair; pulley weld inspection; pulley bearing grease change; replacement of worn cleaner blades, idlers and rubber rings; take-up travel and safety-device check
Major overhaul (6–12 months)Reducer strip, clean and worn-part replacement; pulley lagging re-cast; pulley shell crack inspection and replacement if needed; bearing housing and bearing inspection; frame deformation and weld inspection; belt repair or replacement; chute liner replacement; cleaner blade replacement; electrical and protection overhaul

10.4 Lubrication schedule

PointLubricantTop-upChange
Pulley bearingsZL-2 lithium greaseEvery half monthFlush out the old grease when topping up
Sheave blocksZL-2 lithium greaseQuarterlyFlush out the old grease
Take-up winch bearingsZL-2 lithium greaseQuarterlyFlush out the old grease
Rope grooves and wire ropeZL-2 lithium greaseQuarterly—
Take-up trolley bearingsZL-2 lithium greaseQuarterly—
Electro-hydraulic brakeDB-25 transformer oil—Every 6 months
Pivot pinsHB-30 machine oilWeekly, drip feed—
ReducerN220 or N320 industrial gear oil—Every 6 months
Motor bearingsZL-2 lithium grease—Every 12 months
Fluid couplingNo. 20 turbine oilQuarterlyEvery 12 months

10.5 Taper-lock bush check

On drive and bend pulleys fitted with taper-lock bushes, check every screw's locking torque after the first 500 hours of operation, then every 5,000 hours. A bush that has been allowed to work loose will damage the shaft and the pulley hub, and the repair is far more expensive than the check.

10.6 Pulley bearing reference

Pulley diameter D (mm)Shaft diameter d (mm)Spherical roller bearing
50060 / 80 / 100 / 120 / 14053512 / 53516 / 53520 / 53524 / 53528
63080 / 100 / 120 / 140 / 16053516 / 53520 / 53524 / 53528 / 53532
800120 / 140 / 160 / 180 / 20053524 / 53528 / 53532 / 53536 / 53540
1,000120 / 140 / 160 / 180 / 200 / 220 / 240 / 26053524 / 53528 / 53532 / 53536 / 53540 / 53544 / 53548 / 3053752
The first 500 hours tell you the most. Re-check tension and tracking, check the taper-lock screws, and record baseline temperatures and motor currents. That baseline is what makes a later abnormality obvious.

Frequently Asked Questions

What tolerances matter most when installing a belt conveyor?

Frame centreline straightness, pulley squareness and idler height are the three that decide whether a belt runs centred. Centreline deviation must be within 10 mm for a conveyor up to 100 m and 200 mm at 2,000 m, never more than 5 mm in any 25 m length, and two-thirds of those values on a reversible conveyor. Adjacent idler sets must be within 2 mm of each other and within 5 mm in any 100 m.

How long should a belt conveyor run without load before it is loaded?

At least two hours. During the no-load run, check for rubbing, mistracking beyond 5% of belt width, abnormal noise or vibration, oil leaks, abnormal temperature rise, correct operation of the brake, limit switches and protection devices, even cleaner-blade contact, free movement of the take-up and loose foundation or frame bolts.

How should a belt conveyor be loaded during commissioning?

In stages: about 20%, 50%, 80% and 100% of rated load, with at least two hours of continuous running at each stage. Where the process requires it, a 110% to 125% full-load start and run test is added. Loading gradually lets a fault appear at a controlled load, where it can be corrected, instead of at full production, where it causes damage.

What should I do if the belt mistracks during the load run?

First check that the material is centred on the belt and adjust the chute baffle. Then adjust the carrying and return idlers and the head and tail pulley positions according to the direction of mistracking. If the tension is low, increase it. If these steps do not solve it, check the straightness of the belt and the splice centrelines and re-splice if necessary.

How often should a belt conveyor be maintained?

In addition to daily inspection, a minor service is normally carried out monthly and a major overhaul every six to twelve months, adjusted to the site and duty. Pulley bearings are greased about twice a month, reducer oil is changed every six months, fluid-coupling oil is topped up quarterly, and taper-lock bush screws are checked after the first 500 hours and then every 5,000 hours.