A chain bucket conveyor carries material in steel buckets that are bolted directly to two parallel strands of roller chain. The chain runs on tracks inside a structural frame, the drive at the head pulls the loaded buckets up an incline, and the buckets tip and discharge into a chute at the top. Because the buckets are rigid and the chain is the only traction element, this machine handles abrasive, hot, lumpy and wet material at angles where a belt conveyor would need a very wide belt, a steep cleat profile or simply cannot hold the load. This guide covers the DS chain bucket conveyor from the inside out: how it works, its five subassemblies, how it is erected and aligned, the tolerances that decide whether the chain runs for years or wears out in months, how the running part is installed and tensioned, the no-load and load trials, and the lubrication and wear-part regime after handover. It is based on the Tianyi chain bucket conveyor training manual used by our service engineers on site. For the equipment range itself, see our chain conveyor page.

In this article

1. What a chain bucket conveyor is and how it works 2. The five subassemblies 3. Where a chain bucket conveyor is the right choice 4. Before erection: site, foundation and component check 5. Setting the centreline 6. Erection sequence and alignment tolerances 7. Support, track and rail installation 8. Running part: assembly, installation and chain tension 9. The no-load trial run 10. The load trial run and handover 11. Lubrication, maintenance and wear parts Frequently asked questions

1. What a Chain Bucket Conveyor Is and How It Works

A DS chain bucket conveyor is a continuous bulk-handling machine in which a series of steel buckets is fixed to two endless strands of roller chain. The chains run in upper and lower tracks supported by a steel frame; the buckets travel between the two strands, open side up on the carrying run. Material enters through an inlet at the loading point, falls into the passing buckets, and is carried along the track to the head, where the chain wraps around the head wheel and the buckets turn over, discharging the material into a chute.

The working principle is simple, and that is exactly why the installation matters so much:

The installation decides the service life. On a chain bucket conveyor, the difference between a machine that runs quietly for a decade and one that eats chains is almost never the chain itself. It is the straightness of the frame, the gauge of the tracks, the phase of the two head sprockets and the tension in the two chain strands.

2. The Five Subassemblies

Every DS chain bucket conveyor is built from the same five groups. Knowing what each one does makes the installation sequence obvious, because each group is the reference for the next.

3D model of a DS chain bucket conveyor showing the enclosed head drive unit, twin roller chains, steel buckets on the carrying run and the open support frame
Figure 1. A DS chain bucket conveyor. The drive and head section sit in an enclosed housing at the discharge end; the buckets are bolted to two roller chains that run on tracks carried by the support frame.

2.1 Drive unit

The drive consists of a YE4 series super-high-efficiency motor, a ZSY series parallel-shaft reducer, a large and a small sprocket, and the transmission chain between them. The reducer output drives the head shaft through the sprocket pair; the transmission chain is the part that needs guarding and periodic tension checks.

2.2 Running part

The running part is two rows of sleeve roller chain with integral rollers, plus the buckets. The rollers are part of the chain itself, not separate trolleys, and each bucket is bolted to the side plates of both chains. This is why bucket alignment and chain alignment are the same problem: if the two chains are not parallel and in phase, the buckets sit skew.

2.3 Head

The head group comprises the head casing, head shaft, head wheel, rolling bearings and bearing housings. The head wheel is a one-piece casting in ZG310-570. It carries the full chain tension and transmits the drive torque, so its shaft alignment relative to the frame is critical.

2.4 Tail

The tail group comprises the tail casing, tail shaft, tail wheel, rolling bearings, bearing housings, compression springs and tension screws. The tail wheel is also a one-piece ZG310-570 casting. The screw-and-spring take-up at the tail is the only adjustment for chain elongation, which is why the manual insists that at least half of its travel remains unused after installation.

2.5 Intermediate section and accessories

The intermediate section is the frame that carries everything between head and tail: standard and reinforced connecting supports, legs and brackets, the upper and lower tracks, the upper and lower hold-down rails that keep the chain in contact with the track on curves and inclines, the feed inlet, inspection covers, access doors, the main and secondary discharge chutes, and the local control box.

SubassemblyMain partsWhat it controls
Drive unitYE4 motor, ZSY parallel-shaft reducer, sprocket pair, transmission chainSpeed, torque, starting and stopping
Running partTwin sleeve roller chains with integral rollers, steel bucketsCarrying capacity, bucket spacing, chain life
HeadHead casing, head shaft, cast head wheel, bearingsDischarge, chain direction change, tension load
TailTail casing, tail shaft, cast tail wheel, bearings, springs, tension screwsChain tension and take-up reserve
Intermediate sectionSupports, legs, tracks, hold-down rails, inlet, covers, chutes, control boxChain path, gauge, straightness, dust containment

3. Where a Chain Bucket Conveyor Is the Right Choice

The chain bucket conveyor occupies a specific niche: it is a bucket machine, but unlike a bucket elevator it can run at any inclination, including horizontal sections followed by a steep lift, and it can be loaded at several points along its length. Compared with the other bulk-handling options:

EquipmentPath it can takeBest forWatch out for
Chain bucket conveyorHorizontal, inclined, combined; multi-point loadingAbrasive, hot, lumpy or wet material; steep lifts; heavy bucketsChain and roller wear; frame and track alignment
Belt conveyorHorizontal to moderate inclineHigh tonnage over long distances, low wearIncline limited by material; spillage at steep angles
Bucket elevatorVertical onlyHigh lift in a small footprintCannot take horizontal runs; sensitive to wet, sticky feed
En-masse conveyorHorizontal, small inclines, L, Z and loop layoutsFines and powders in a closed casing, gentle handlingNot for large lumps or very abrasive material

Typical duties are furnace and boiler ash, slag and clinker, limestone and lime, coke, mineral ore, sand and gravel, and other abrasive or hot granular materials where the buckets protect the material from the frame and the frame protects the plant from the material.

4. Before Erection: Site, Foundation and Component Check

The manual is blunt about preparation: the installation site must be cleaned before work starts, and every component must be checked for completeness, damage and deformation. Anything damaged or distorted must be repaired before it is installed — not after it is in the air.

Do not lift the head or tail before the centreline exists. Both groups are aligned to the same wire. If the wire is set after one of them is fixed, that group becomes the reference by accident — and every tolerance downstream is measured from the wrong line.

5. Setting the Centreline

The longitudinal centreline is the single reference for the whole machine: head, tail, every support, both tracks and the running part. The manual requires a theodolite, not a chalk line, because the tolerances are in millimetres over tens of metres.

  1. Mark the intersections. Establish where the conveyor longitudinal centreline crosses the head centreline and the tail centreline. These two points define the machine axis.
  2. Mark along the axis. Set the theodolite on the axis and mark a point on the foundation every 10 m along the conveyor.
  3. Stretch the wire. Above these marks, stretch a fine steel wire. The wire is tensioned between points about 3 m beyond the head shaft and 3 m beyond the tail shaft, with plumb bobs hung from it so the wire can be transferred down to the machine.
  4. Verify and protect. Check the wire against the marks at several stations, then protect it — a knocked wire invalidates every alignment done against it.

Every alignment step that follows refers back to this wire. When the manual says "the longitudinal centreline (fine steel wire)", it means this one, and it must still be in place until the frame is fully welded and bolted.

6. Erection Sequence and Alignment Tolerances

Installation starts at the tail and works toward the head. The reason is practical: the tail is the tensioning end and the reference for the track line, and the head is heavy enough that it should be positioned against an already-established frame rather than the other way round.

6.1 Tail alignment

The tail is normally supplied as a complete assembly. Before setting it down, confirm that the sprocket set screws are tight and that the two sprockets are in phase. The tail is correctly aligned when three conditions are met simultaneously:

The method is a sequence of three measurements:

  1. Level the shaft. Set the tail shaft level with a spirit level, adjusting with shims between the tail casing and the foundation. Shims are not supplied with the machine. Permissible level error: 0.3/1000 of the bearing span.
  2. Square the shaft to the wire. Place a straightedge of at least 2 m against the machined side face of the sprocket and clamp it temporarily. Measure the distance from each end of the straightedge to the wire. Adjust the tail until the two distances are equal and each equals half of X, where X is the distance between the two sprocket side faces — at that point the wire passes through the centre between the sprockets. Permissible perpendicularity error: 1/1000 of the bearing span.
  3. Fix the tail frame. Only when both conditions are met, anchor the tail frame.

6.2 Head alignment

The head is lifted into position as a complete assembly and aligned by exactly the same three criteria and with the same tolerances as the tail: level shaft, shaft perpendicular to the wire, wire through the midpoint between the sprockets. Check the sprocket set screws and the phase of the two sprockets before lifting. Once aligned, tighten the connecting bolts.

6.3 Drive installation

  1. Weld the drive frame to the supporting structure (in ash-handling installations, typically the top of the slag silo) and make sure the top face of the drive frame is level.
  2. Mount the motor-reducer on the drive frame.
  3. Fit the transmission chain over the two sprockets.
  4. Position the chain tensioner so that the roller face is parallel to the axis of the chain links, then weld the tensioner to the frame.
  5. Adjust the tensioner, fit the chain guard and fix it.

The reducer output shaft and the head shaft must be parallel, and the centres of the large and small sprockets must lie on one straight line. A transmission chain that runs at an angle wears the sprocket teeth on one side and will fail long before the conveyor chain does.

Inclined DS chain bucket conveyor installed in a plant between two steel staircases, with red steel buckets on twin roller chains, side rollers and the head section at the top of the tower
Figure 2. An inclined chain bucket conveyor installed between stair towers. The buckets are bolted to both chain strands, the rollers run on the side tracks, and the head section at the top of the incline discharges into the chute.

7. Support, Track and Rail Installation

The supports carry the tracks, and the tracks carry the chain. Errors at support level are multiplied along the machine, so the manual sets tolerances here that are tighter than anything on a belt conveyor frame.

7.1 Connecting supports

Inspect every support for transport damage before installation; any twist must be corrected. Then install to these limits:

CheckTolerance
Support centreline coincident with conveyor longitudinal centreline (wire)≤ 1 mm
Height difference of the upper track pads on two adjacent supports, measured perpendicular to the foundation≤ 1/1000 of the support spacing, and ≤ 5 mm over the full conveyor length
Perpendicularity of the support plane to the longitudinal centreline (wire)≤ 1/1000 of the support width
Relative height difference between the two track pads on the same support≤ 1/1000 of the track gauge

7.2 Tracks

Tracks are installed from the tail toward the head, following the track drawing, after the supports are in place. Before installation, every track section must be straightened; it is not acceptable to pull a bowed section into line with the bolts.

CheckTolerance
Track straightness before installation0.5/1000 of the measured length, and ≤ 3 mm over the full length
Level of the top faces of the two tracks in the same cross-section≤ 0.5/1000 of the track gauge
Symmetry of the two parallel tracks about the longitudinal centreline≤ 1 mm
Track gauge±1 mm
Weld after measuring, never before. Once the track is welded to the pads, the gauge and the line are fixed. If the frame has to be corrected afterwards, the welds have to be cut — and the paint, the pad and often the track section are lost with them.

8. Running Part: Assembly, Installation and Chain Tension

The running part ships as loose components: chain links, buckets and the bolt sets that join them. Assembly is straightforward, but two details decide whether the machine runs true.

8.1 Assembling the running part

8.2 Two installation methods

The manual gives two methods; which one applies depends on whether there is space behind the tail.

Method A — pull the assembled run in from the tail. If there is enough room at the tail, extend the lower track to the foundation, assemble the running part outside the machine and pull it in with a rope. On an inclined conveyor, the run must be restrained at all times so that it cannot slide or run back.

Method B — feed the run in through an upper-track opening. Remove, or leave out during erection, a section of upper track at a convenient position. Feed the assembled running part through the gap and pull it along with rope, hooks or a hoist. On an incline, once the run has passed the sprocket, the two sides are no longer balanced and the chain can run back — restrain it before releasing the pull.

8.3 Tensioning the chain

When the running part is fully installed, both chains must be tensioned — equally and by the same amount. Tensioning one strand harder than the other skews every bucket and overloads one chain.

8.4 Safety and auxiliary devices

Before the trial run, every safety and auxiliary device that does not interfere with inspection must be fitted — chain guards over the transmission, covers over the running part, and the guards at the head and tail. A machine is not ready to jog because the chain turns; it is ready when nothing exposed can be reached.

9. The No-Load Trial Run

The no-load run proves the geometry. It is not a formality: most installation errors — a reversed motor, a chain running to one side, a bucket fouling a cover — appear in the first few revolutions.

9.1 Before the first start

Clean all debris out of the conveyor, provide lighting along the line, and assign the crew. Then check, item by item:

9.2 Running the test

Run continuously for about 8 hours. Start with jogging: press and release, watch, and deal with any problem immediately. Only when the jog starts are clean should the machine be run continuously.

During the run, check and record:

MeasurementLimit during no-load run
Bearing temperature rise≤ 30 °C
Reducer temperature rise≤ 45 °C
Current, voltage, powerRecord, and compare with the design figures

After the no-load run, re-tighten every connecting bolt, and spot-weld the nuts on the bucket-to-chain bolts. Vibration will loosen a bolted bucket joint over time; the spot weld is what keeps the bucket on the chain.

10. The Load Trial Run and Handover

The load test starts only after the no-load run has passed. It lasts about 8 hours at design feed rate.

10.1 Starting procedure

  1. Start the chain bucket conveyor.
  2. Feed material into the buckets gradually. Never drop a full load onto the running part at once, and never start a loaded machine.

10.2 Normal stopping procedure

  1. Stop the feed.
  2. Let the conveyor run until the buckets are completely empty.
  3. Stop the conveyor.

A machine stopped with full buckets restarts against the full weight of the material, and on an incline it may run back before the drive takes up. Emptying before stopping is not a convenience; it is part of the operating procedure.

10.3 What to check under load

After the load run, re-check the chain tension. Only when everything is normal is the conveyor handed over for operation.

Record the baseline, not just the pass. Write down the current, voltage, power, bearing temperatures and chain tension at the end of the no-load run and at full load. Those two sets of numbers are the reference for every maintenance decision afterwards — a rising current at the same throughput is the earliest sign of a chain or track problem.

11. Lubrication, Maintenance and Wear Parts

11.1 Lubrication schedule

PointLubricantIntervalMethod
Bearings at all rotating pointsWater-resistant grease500 hoursApply by hand
Open transmission chain, large and small sprocketsWater-resistant grease1.5 monthsApply by hand
Take-up screw and nutWater-resistant grease1.5 monthsApply by hand
Take-up guide railGraphite grease2 monthsApply by hand
ReducerCKD 220 or CKD 3204 monthsPour in

11.2 Reducer oil

For a typical ZSY180-63-BSP reducer the oil charge is 14 litres, with the grade chosen by ambient temperature: L-CKD220 for 0–35 °C and L-CKD320 for 35–50 °C. The reducer is not filled at the factory.

11.3 Routine maintenance

Keep the machine and the area around it clean, and clear spillage at the tail promptly. Spillage at the tail is both a housekeeping problem and an early warning: it usually means the chain is slack, the loading point is off-centre, or a bucket is deformed.

ItemWhat to do
Take-up screwAfter every tension adjustment, coat the threads of the screw and nut with grease. Oil may be dripped on the chain during operation if needed.
Bearing housingsLook, listen and touch. Check that the housing is firmly fixed; if it feels too hot, find the cause and correct it.
SprocketsWatch the meshing at the head and tail wheels and listen for abnormal noise.
Carrying rollersCheck that they roll on the track. Sliding or rail gouging must be corrected immediately.
ChainCheck tension. A worn chain must be re-tensioned promptly, or it will wear much faster.
BucketsCheck for deformation, cracks and loose bolts.

11.4 Electrical protection

The thermal overload relay is set so that the machine trips before a jam damages the chain:

Current vs. set valueApproximate trip time
1.05 ×About 2 hours
1.2 ×Less than 2 hours
1.5 ×Less than 4 minutes
7.2 ×4–10 seconds

11.5 Wear parts to keep in store

PartSpecificationQuantity per machineReplacement rule
Head bearingGB/T288 type 222242On condition
Tail bearingGB/T288 type 222192On condition
Head wheelSDB80.2-32On wear
Tail wheelSDB80.3-22On wear
Running partChain and buckets as a set—Replace the whole chain at end of life. If the take-up travel is used up, remove 2 chain links with their buckets.
Chain rollersAs per drawing—Replace when the roller face has worn to the limit shown on the drawing

Sprocket tooth blocks must be replaced when the tooth wear exceeds 6 mm, or when the chain no longer leaves the sprocket cleanly. A worn tooth profile makes the chain climb, which loads the next tooth in line and accelerates wear across the whole wheel.

Frequently Asked Questions

What is a chain bucket conveyor used for?

A chain bucket conveyor carries abrasive, hot, lumpy or wet bulk material in steel buckets bolted to two roller chains. It handles horizontal, inclined and combined paths, can be loaded at several points, and is typically used for boiler ash, slag and clinker, limestone, coke, ore, sand and gravel where a belt conveyor would struggle with the incline or the material.

Which tolerances matter most when installing a chain bucket conveyor?

The four that decide chain life are: support centrelines within 1 mm of the conveyor centreline; track straightness within 0.5/1000 of the measured length and 3 mm overall; track gauge within plus or minus 1 mm with the two tracks symmetrical to within 1 mm; and the head and tail shafts level to 0.3/1000 and perpendicular to the centreline to 1/1000 of the bearing span, with both sprockets in phase.

How tight should the chains be on a chain bucket conveyor?

Both chains are tensioned equally, and the correct tension is judged at the point of lowest tension near the tail: a slight sag in the horizontal section means the tension is right. On inclined sections all carrying rollers must stay on the track, with none hanging free. The take-up must still have at least half of its travel available for future chain elongation.

How long do the no-load and load trial runs take?

The no-load run lasts about eight hours after the initial jog starts, with bearing temperature rise limited to 30 degrees Celsius and reducer temperature rise to 45 degrees Celsius. The load run also lasts about eight hours, with bearing temperature rise limited to 40 degrees Celsius, two to three abnormal stops to verify the backstop, and a final chain tension check before handover.

When should the chain, sprockets and rollers be replaced?

Replace the running part as a complete chain at the end of its service life; if the take-up travel is exhausted, remove two chain links together with their buckets. Replace sprocket tooth blocks when tooth wear exceeds 6 mm or the chain no longer leaves the sprocket cleanly, and replace chain rollers when the roller face reaches the wear limit on the drawing.

Planning a Chain Bucket Conveyor Installation?

Send us the material, lump size, temperature, capacity, incline and layout. Our engineering team will confirm the bucket size, chain type, track arrangement and drive, and supply the installation drawings, the commissioning procedure and the wear-part list for the machine.

Request a Chain Bucket Conveyor Proposal